Like most other projects on our national railway network it is running late and over budget, but later this month the splendid semaphore signalling along ten miles of main line from Gilberdyke to Ferriby, on the north bank of the River Humber, will finally disappear, as control of the route passes to the Railway Operating Centre at York.
It will come as no surprise to those who read my September 2017 feature “Humberside re-signalling delayed” – which, incidentally, provoked outrage from one local NR manager at the time – to see that the planned spring 2018 completion date has been missed by eight months.
But it is also interesting is to see that what was billed as a £34.5 million project when contracts were first let in February 2016 has, according to the most recent Network Rail press release, now become a £50 million project. Continue reading “Goodbye Gilberdyke”